Help & Support » Guides » User Guide » Modules » Projects » Project Schedule

Project Schedule

The Project Schedule offers a Gantt-style overview of your Project's Milestones and Tasks, allowing you to quickly and visually track your Project's progress.  

Using this guide, you can:

Planned, Predicted, Target and Actual Dates

Accelo's predictive scheduling tool uses five different dates to track and schedule your projects in real-time.  Those dates are:

  • Planned:  When the work was originally scheduled to begin and end. 

    This baseline date is set by the project manager via the Project Plan and acts as the basis for all other date calculations.  The Planned Dates also determine when the Task will first appear on your team's schedule.
  • Predicted: The date when work is likely to actually start or end. 

    Predicted Dates are used to present you with an estimation of your Project's future timeline, and are calculated using the Task's Planned Start and Due Date, its Duration and its Dependencies.  Predicted Dates will initially be the same as the Planned Dates when work first begins, but will be updated as the Project progresses.  If the Task is not started by the Planned Start Date, or if the Task's Dependencies have not been satisfied on time, the Predicted Start Date will automatically move backward by one day (one day later).  The Predicted Due Date will move backward by one day at a time if the Task is not started by the Planned Start Date, or if Dependent Tasks are running late.
  • Target: The date when the assignee could reasonably start or complete work.

    Project delivery is often a team sport, and it often doesn't make sense to look only at the whole project to understand who is responsible for it being ahead or behind schedule. Especially in the case of upstream delays, it isn't fair to a team member whose work is done later to be blamed for delays caused by upstream work which they're not responsible for.  To better track these situations, Target Dates track the date when work could reasonably be started or completed based on the original Planned Date and dependencies.  If a dependency causes work to be delayed or start early, the Target Dates will reflect the date when dependencies would allow that work to first begin.  For example, if a dependency pushed a Task back by two weeks, then the Target Dates would be two weeks later than the Planned Dates.

  • Commenced & Completed - Actual: The date when work was marked Started and Complete.

    The Actual dates are used to identify when work was actually performed, i.e. when a Task was Started or a Milestone Completed.  Actual Dates will not be set until work is marked Started or Complete.  Completing a Task outside of its Planned Dates will update the Predicted Date for any dependent Tasks or Milestones.  
  • User Estimated: Dates set manually by staff members.

    One of the philosophical tenets of Accelo is that the people actually doing the work are in the best position to know the reality on the ground. User Estimated dates allows your team members to update their Tasks with the dates which they expect work to actually begin or end, not simply based on pre-set dependencies or Planned Dates.  These dates will also update your team's schedule, re-allocating budgeted time based on the available dates.  User Estimated dates can be controlled and disabled by the Project's Level of Editing

The Project Schedule offers a quick and visual tool for staying on top of these complex schedules by incorporating these dates for a comprehensive overview of your Project's schedule.  To do that, each line of the schedule includes the time frame which that work is expected to occur, offering insight into where potential scheduling issues may occur.

schedule plain2

Each date is shown using a special format:

  • Solid Black Line: Planned Dates 
  • Dotted Line: Predicted Dates 
  • Dotted Outline: Target Dates
  • Solid Outline: Actual Dates
  • Black or White Circle: User Estimated Dates

The Gantt also uses color coding to identify whether these dates are behind or ahead of schedule:

  • Green: Ahead of Schedule
  • Orange: Expected to Complete Behind Schedule
  • Red: Actively Behind Schedule

For more information on how these dates are used to schedule your team, check out Dynamic Scheduling.

Using Schedule Filters

To help simplify your complex projects, and focus on specific details and work, the Schedule offers several filters:

filters2

  • Search: Search the title of your Milestones and Tasks for specific work
  • Planned/Predicted: Toggles the Planned and Predicted Dates appearing for each line of the Schedule
  • Target/Actual: Toggles the Target and Actual Dates appearing for each line of the Schedule
  • My Work Only: Shows only Milestones and Tasks which you are either assigned to, or manage
  • Hide Complete: Hides all Milestones and Tasks which have been completed
  • Showing Day/Week: Changes the schedule's time frame to view either individual days, or full weeks
  • Go To Today: Jumps the view to "today"
  • Fullscreen: Expands the schedule to take up the full page

 

Understanding Boundary Dates

 When viewing or editing Tasks within a project, you may notice some tasks display Boundary Dates, meaning the Task Start Date and Task End Date must fall within these boundary dates.

Typically these are the Planned dates of the parent object (usually a milestone, but possibly the project itself) but if a Deadline date has been set then this will be used rather than the Planned Due date.

The consequence is that users wanting to move tasks around will be limited to these boundary dates. If the tasks really should be moved, then it's better to update this in the project plan so that the flow-on effects can be fully realized according to the project dependencies, etc.

Accelo uses cookies to give you the best possible experience - by clicking 'Continue' you agree to our use of cookies. Refer to our Privacy Policy for details. Continue